Secondary Pedestal Installation:  PRMC & PSP

PRMC, PSP, and PSPF Installation:

PRMC-190-MG install03

PSP-151530-MG install

PSPF Installation

PRMC

PSP

PSPF

  1. Excavate the hole approximately 2” - 4” deeper than the suggested pedestal burial depth.
  2. Compact the soil.
  3. Add approximately 2”- 4” of gravel to the bottom of the hole.
  4. Compact and level the gravel.
  5. Place the pedestal into the hole.
  6. Level the pedestal.
  7. Back-fill with loose earth material.
  8. Do not back-fill with chunks of frozen material or large rocks next to the pedestal.
  9. Pack the back-fill material by foot tamping.